updates

RISE    updates    THE PLAN    GIVE    FAQ     SERIES


February 2020

Concrete is now poured in the office & children areas (LSM & TeamKID).  Next to be poured will be the Lobby & auditorium.  Framing is up in the children's wing. Roof Trusses will start to go up any day. Plumbing & Electric underground work are still underway in the rest of the building.


The weather has been an issue lately. Please continue to pray for God's timing and His will as we move forward.


January 2020


Sewer & Water connections installed, concrete pads in Children's wing were poured, framing for small children areas went up.


December 2019

Roof decking went up!  Underground Electric & Plumbing was installed under children's wing (with bathrooms in every children's room).   


November 2019

Steel is all up, plumbing has started in the children's wing


October 2019

Poured our foundation, walls and piers.  Foundation block walls went in & sleeves were installed for utility routing.  


September 2019

The majority of underground piping is complete.  Prepping for digging the footers. 


August 2019

Storm water management installed, grading finished, sediment pond finished


July 2019

site work & sediment pond started


June 2019

clearing began, prep work initiated.


May 2019

Permits!


April 2019

With God's help, LifeHouse Church was able to raise a $2 million deposit by April 7, 2019.  This allowed us to hold our ground-breaking celebration in April!  




We are trusting God to provide the remaining funds through His people.  

Would you consider making an investment into RISE?